Analisis Kinerja Waktu dan Faktor Kendala Pelaksanaan Proyek Jalan Lingkar Inner Ring Road Kota Kendari dengan Metode CPM MSR dan RII

  • Sufrianto Sufrianto Universitas Sulawesi Tenggara
  • Syamsuddin Syamsuddin Universitas Sulawesi Tenggara
  • Nurhikmah Alam Universitas Sulawesi Tenggara
  • Muhamad Armanto Universitas Sulawesi Tenggara
Keywords: Critical Path Method, critical path, Mean Score Ranking, Relative Importance Index

Abstract

Construction project success depends on effective control of time, cost, and quality. This study analyzes schedule performance and time efficiency and identifies the dominant constraints affecting the Kendari City Inner Ring Road Project. The study focuses on 6.20 km of rigid pavement with a planned duration of 24 weeks. A quantitative descriptive approach was used. Secondary data consisted of work items and durations, time schedules, S-curves, progress reports, and design drawings, while primary data were obtained through observation, documentation, and questionnaires distributed to 25 project personnel. Schedule performance was evaluated using Planned Progress, Actual Progress, Schedule Variance (SV), Schedule Performance Index (SPI), schedule-baseline deviation, and Time Deviation. Critical activities were identified using the Critical Path Method (CPM), while constraint factors were ranked using Mean Score Ranking (MSR) and Relative Importance Index (RII). Delays occurred in weeks 8, 9, 11, 16, 17, and 22. The largest progress deviation was -6.79% in week 16 and the lowest SPI was 0.88 in week 8. The project was completed in 24 weeks with 100% final progress, final SPI of 1.00, zero final time deviation, and 100% final time efficiency. Average SPI was 0.9846 (98.46%). The critical path was A-B-C-D-E-F-G-H-I-J-K-L-Q with a duration of 24 weeks and zero float. Delayed material procurement was the dominant constraint (MSR 4.08; RII 0.816), followed by labor productivity and weather conditions.

Downloads

Download data is not yet available.
Published
2026-11-23
How to Cite
Sufrianto, S., Syamsuddin, S., Alam, N., & Armanto, M. (2026). Analisis Kinerja Waktu dan Faktor Kendala Pelaksanaan Proyek Jalan Lingkar Inner Ring Road Kota Kendari dengan Metode CPM MSR dan RII. Sultra Civil Engineering Journal (SCiEJ), 7(2), 348-355. https://doi.org/10.54297/sciej.v7i2.1626